                                    Legend:

                                    OD -

                                    Owner or Developer of project

                                    PD -

                                    Project Director, Owner's representative

                                    LAC -

                                    Lead Architect or Consultant

                                    PCM -

                                    Project Construction Manager

                                    JA -

                                    Jurisdictional Authorities

                                    denotes primary responsibility

                                    denotes significant supporting responsibility

                                    Published here July, 2002.

                                    Introduction | Pre-Project Study | Concept Phase
                                    Concept Development | Schematic Design | Final Design | Tender & Award
                                    Construction | Project Commissioning & Finishing

                                    4.0     Project Commissioning & Finishing

                                    • Unlike earlier phases, the boundary between this and the preceding phase is less distinct. Nevertheless, the activities in this period are sufficiently different to warrant attention as a separate phase.

                                    • In this Phase, integration of Project and Technical Management and the owner's Takeover Activities is even more important as the focus moves back to the owner.

                                    • The owner must be ready with trained staff to take over the "care, custody and control" of the final facility. Hence, in this phase especially, 'OD' refers to the owner and/or its operators.

                                    Ref #

                                    Task

                                    Responsibility »

                                    OD

                                    PD

                                    LAC

                                    PCM

                                    JA

                                    4.1.0

                                         Project Management

                                    4.1.1

                                    Advise owner of expected transfer date

                                     

                                    4.1.2

                                    Obtain maintenance manuals & operating instructions

                                         

                                    4.1.3

                                    Liaise with operating staff manager to arrange training

                                         

                                    4.1.4

                                    Obtain guarantees

                                         

                                    4.1.5

                                    Obtain 'As-built drawings'

                                         

                                    4.1.6

                                    Coordinate commissioning, testing, balancing, all systems

                                       

                                    4.1.7

                                    Obtain occupancy certifications & permit

                                     

                                    4.1.8

                                    Arrange acceptance & approval of completed building

                                     

                                    4.1.9

                                    Transfer facility to owner's "care, custody & control"

                                         

                                    4.1.10

                                    Arrange final photographs & publicity releases

                                         

                                    4.1.11

                                    Arrange opening ceremonies

                                         

                                    4.1.12

                                    Establish reasonable dates for Total Performance

                                         

                                    4.1.13

                                    Verify all deficiencies & outstanding documents completed

                                         

                                    4.1.14

                                    Approve final payments to contractors

                                         

                                    4.1.15

                                    Make final payments to contractors

                                         

                                    4.1.16

                                    Perform final accounting

                                       

                                    Ref #

                                    Task

                                    Responsibility »

                                    OD

                                    PD

                                    LAC

                                    PCM

                                    JA

                                    4.2.0

                                         Technical Management

                                    4.2.1

                                    Prepare final deficiency lists

                                         

                                    4.2.2

                                    Ensure contractors rectify deficiencies

                                         

                                    4.2.3

                                    Verify completeness of manuals & operating instructions

                                       

                                    4.2.4

                                    Verify correctness of guarantees

                                         

                                    4.2.5

                                    Verify correctness of 'As-built drawings'

                                         

                                    4.2.6

                                    Supervise commissioning, testing, balancing, all systems

                                       

                                    4.2.7

                                    Provide support to operator training (as needed)

                                         

                                    4.2.8

                                    Liaise with Jurisdictional Authorities for certificates, permits

                                         

                                    4.2.9

                                    Provide consultation to owner during startup

                                         

                                    4.2.10

                                    Inspect & assess deficiencies to verify Total Performance

                                         

                                    4.2.11

                                    Issue Certificate of Total Performance

                                       

                                    4.2.12

                                    Verify all guarantees, manuals, documentation received

                                         

                                    4.2.13

                                    Certify Total Performance & recommend holdback releases

                                         

                                     

                                         Post-Project Support

                                     

                                    Assist in expediting guarantee items (as required)

                                         
                                     

                                    Conduct post-project project management audit

                                       
                                     

                                    Provide continuing technical consultation

                                         

                                    Construction  Construction

                                    Home | Issacons | PM Glossary | Papers & Books | Max's Musings
                                    Guest Articles | Contact Info | Search My Site | Site Map | Top of Page 

                                                                      car

                                                                      Premier League

                                                                      city

                                                                      explore

                                                                      explore

                                                                      fashion

                                                                      game

                                                                      Super League

                                                                      Super League